01 / Describe the productLiquid name and composition; viscosity with measurement temperature; density; Brix; solids or crystals; foaming, oxidation and air-contact limits.
02 / Define the production dutyAverage and peak flow; batch volume; operating hours; upstream feed pattern; permitted discharge interruptions and standby expectations.
03 / Map the transfer routeSource and receiver levels; total pipe length; internal diameter; elevation; bends, valves and restrictions; receiver pressure and venting.
04 / Confirm utilitiesSustained compressed-air capacity and pressure at the point of use; air quality; electrical supply; available heating and cleaning utilities.
05 / Agree construction & controlsWetted materials; surface finish; cleaning method; insulation; vessel arrangement; DCS interface; hazardous-area requirements if any.
06 / Set the delivery scopeSite country, documentation requirements, factory testing, installation responsibilities, acceptance plan and target project schedule.